tva logoTennessee Valley Authority
""

Watts Bar Unit 2

The completion of Watts Bar Nuclear Plant Unit 2 continues to meet targets for safety, quality, cost, and schedule. Once complete, the unit will produce the first new nuclear generation of the 21st century in the United States — generation that is low-cost and carbon-free.

photo

Nuclear Regulatory Commission Chairman Allison Macfarlane visited Watts Bar 2 to get a firsthand look at progress to bring the unit online by December 2015. She and NRC staff toured both units at the site, including new safety features being installed.

photo

Big Move — Crews work to install huge 28-inch thick, 47-ton concrete and steel doors at Watts Bar Nuclear Station. The doors are part of a building to protect emergency diesel generators that provide backup electricity for the plant. It is designed to withstand 360 mile-per-hour winds and flying debris.

Schedule

Open vessel testing at Watts Bar 2 was the first of several major milestones to be completed toward the goal of commercial operation by December 2015. Watch the time-lapse video below that shows approximately 185,000 gallons of water flowing into the Watts Bar Unit 2 reactor vessel over a 23-minute period of testing on July 1.

 

When completed Watts Bar 2 will generate 1,150 megawatts of electricity — enough for about 650,000 homes.

Safety

Nearly 3,200 people work on Watts Bar 2 construction. They’ve worked more than 27.5 million hours without a lost-time incident.

Watts Bar 2 will be the first nuclear plant in the U.S. to meet new Nuclear Regulatory Commission regulations established after the 2011 earthquake and tsunami that struck Fukushima Nuclear Plant in Japan. 

Quality

Quality of work remains high with a quality control acceptance rate greater than 98 percent.

Cost

The project is within budget. The total cost of the Watts Bar 2 project is estimated at $4 billion to $4.2 billion.

Watch this video to see more of what’s been happening at Watts Bar 2.

View previous Watts Bar 2 updates

TVA's confidence in the new completion schedule

TVA has high confidence in the new completion schedule and cost estimates for Watts Bar Nuclear Plant Unit 2.

The estimate to complete — called the ETC —  was prepared in collaboration with TVA’s construction contractors and outside experts. The ETC includes:

  • A root-cause analysis of factors that took the project off track
  • A detailed estimate of the costs and time needed to complete the remaining work
  • Estimates for the amount of materials (e.g., conduit, cable, piping) still to be installed, support activities (e.g., scaffolding, painting) and labor rates

Why TVA needs more nuclear power

Nuclear is the best technology for keeping reliability high and rates competitive. It is cleaner than coal and produces no harmful greenhouse gases. And while expensive and complicated to build, nuclear units are economical to operate.

Industry-wide, nuclear is second only to hydroelectric in low production, fuel, and operations and maintenance costs.

By increasing nuclear generation, pursuing renewable energy sources and promoting energy efficiency, TVA will rely less on coal, continue steady progress in reducing air emissions and provide reliable, economical power for the people of our region.

How Watts Bar 2 will help

Completing Watts Bar 2 will put an existing asset to work for TVA customers and add more than 1,100 megawatts of safe, clean, reliable and economical base load generating capacity to the TVA power system.

Watts Bar 2 will help meet the demand for electricity in the Tennessee Valley, with low-cost, carbon-free electricity. It will help replace older, more costly and less efficient coal units that are being retired.

One nuclear unit can make as much electricity as five to 10 coal units without carbon emissions. It is estimated that Watts Bar 2 will help TVA avoid coal-fired emissions of 6 million to 8 million tons of carbon dioxide a year.

Vital statistics about Watts Bar Unit 2

Plant site

  • Location: Near Spring City in southeastern Tennessee
  • Acreage: 1,700-acre site on Chickamauga Reservoir

Cooling towers

  • Quantity: 2
  • Height: 506 feet
  • Diameter: 405 feet at ground level
  • Water flow: 410,000 gallons per minute

Switchyard

  • 500,000-volt transmission lines: 5
  • 161,000-volt transmission lines: 2

Plant design

  • Westinghouse pressurized water reactor that is expected to generate 1,150 megawatts (summer net capability)
  • Reactor core holds 193 fuel assemblies, each containing 264 fuel rods

Reactor vessel

  • Height: 43.8 feet
  • Weight: About 265 tons (empty)
  • Inside diameter: 14 feet
  • Steel thickness: About 9.4 inches
  • Operating temperature: About 586 degrees Fahrenheit
  • Operating pressure: About 2,235 pounds per square inch

Primary containment

  • Inside height: 197.3 feet
  • Inside diameter: 115 feet
  • Steel inner thickness: 1 inch
  • Design pressure: 15 pounds per square inch

Steam generators

  • Quantity: 4
  • Height: 67 feet 8 inches
  • Weight: About 380 tons
  • Operating temperature: About 600 degrees Fahrenheit
  • Operating pressure: 1,000 pounds per square inch

Main generator

  • Height: 16 feet
  • Length: 40 feet
  • Stator weight: About 1,000 tons
  • Rotor weight: About 200 tons
  • Ratings: 1,411 megawatts, 24,000 volts
  • Speed: 1,800 rotations per minute

Steam turbines

  • High pressure: A single eight-stage double-flow axial turbine
  • Low pressure: A series of three, eight-stage double-flow axial turbines
  • Maximum blade diameter: 16 feet
  • Rotor weight: About 177 tons

Main condenser

  • Tubes: About 27,410
  • Tube length: About 115 feet
  • Tube diameter: 1 inch

 

Content for id "future1" Goes Here
Content for id "future2" Goes Here
Content for id "future3" Goes Here