tva logoTennessee Valley Authority
""

Watts Bar Unit 2

The completion of Watts Bar Nuclear Plant Unit 2 continues to meet targets for safety, quality, cost, and schedule. The project recently completed a major testing milestone of key safety systems called Open Vessel Testing and construction of one of the first functional FLEX emergency equipment storage buildings in the industry. Once operational, Watts Bar 2 will produce the first new nuclear generation of the 21st century in the United States — generation that is low-cost and carbon-free.

photo

Several members of TVA’s Regional Energy Resource Council (RERC) recently toured Watts Bar, learning firsthand how completing Watts Bar 2 will add to the Tennessee Valley’s energy diversity, sustainability, and reliability. The group saw the core barrel that will be placed inside the vessel during the upcoming reactor assembly.

 

 

Schedule

Open Vessel Testing at Watts Bar 2 was the first of several major testing milestones to be completed toward the goal of loading fuel and achieving commercial operation by December 2015. The time-lapse video below shows approximately 185,000 gallons of water flowing into the Watts Bar Unit 2 reactor vessel over a 23-minute period of testing on July 1, 2014.

 

Watts Bar team members now are reassembling the reactor in preparation for a second major milestone test, Cold Hydrostatic Testing. Cold Hydro verifies that welds, joints, pipes, components of the Reactor Coolant System and associated high-pressure systems meet quality standards.

When completed Watts Bar 2 will generate 1,150 megawatts of electricity — enough for about 650,000 homes.

Safety

Nearly 3,100 people work on Watts Bar 2 construction. The Watts Bar 2 team has worked more than 28.8 million hours without a lost-time incident.

workers  

Watts Bar 2 will be the first nuclear plant in the U.S. to meet new Nuclear Regulatory Commission regulations established after the 2011 earthquake and tsunami that struck Fukushima Nuclear Plant in Japan. Watch the construction of one of the first functional FLEX buildings in the industry, complete with a 16-foot tall tornado-proof door, designed to protect emergency equipment.

photo

Big Move

Crews work to install huge 28-inch thick, 47-ton concrete and steel doors at Watts Bar Nuclear Plant. The doors are part of a building to protect emergency diesel generators that provide backup electricity for the plant. The building is designed to withstand 360 mile-per-hour winds and flying debris.

 

Quality

Quality of work remains high with a quality control acceptance rate greater than 98 percent in July 2014. In the coming months, additional tests and inspections will ensure that Unit 2 systems operate as designed and that Watts Bar 2 is ready to begin generating electricity for the Tennessee Valley in late 2015.

Cost

The project is within budget. The total cost of the Watts Bar 2 project is estimated at $4 billion to $4.2 billion.

Challenges

As with any complex project, there are challenges and risks associated with completing Watts Bar 2. The Watts Bar 2 team is prepared with a plan to identify, assess, and address challenges and risks as they arise. Challenges include:

  • Completing complex work while protecting safe and reliable operation of Unit 1, the operating unit
  • Completing systems for pre-operational testing during a compressed time period while maintaining safety and quality standards
  • Preparing for upcoming testing milestones
  • Addressing emergent work during testing activities

 

View previous Watts Bar 2 updates

TVA's confidence in the new completion schedule

TVA has high confidence in the new completion schedule and cost estimates for Watts Bar Nuclear Plant Unit 2.

The estimate to complete — called the ETC —  was prepared in collaboration with TVA’s construction contractors and outside experts. The ETC includes:

  • A root-cause analysis of factors that took the project off track
  • A detailed estimate of the costs and time needed to complete the remaining work
  • Estimates for the amount of materials (e.g., conduit, cable, piping) still to be installed, support activities (e.g., scaffolding, painting) and labor rates

Why TVA needs more nuclear power

Nuclear is the best technology for keeping reliability high and rates competitive. It is cleaner than coal and produces no harmful greenhouse gases. And while expensive and complicated to build, nuclear units are economical to operate.

Industry-wide, nuclear is second only to hydroelectric in low production, fuel, and operations and maintenance costs.

By increasing nuclear generation, pursuing renewable energy sources and promoting energy efficiency, TVA will rely less on coal, continue steady progress in reducing air emissions and provide reliable, economical power for the people of our region.

How Watts Bar 2 will help

Completing Watts Bar 2 will put an existing asset to work for TVA customers and add more than 1,150 megawatts of safe, clean, reliable and economical base load generating capacity to the TVA power system.

Watts Bar 2 will help meet the demand for electricity in the Tennessee Valley, with low-cost, carbon-free electricity. It will help replace older, more costly and less efficient coal units that are being retired.

One nuclear unit can make as much electricity as five to 10 coal units without carbon emissions. It is estimated that Watts Bar 2 will help TVA avoid coal-fired emissions of 6 million to 8 million tons of carbon dioxide a year.

Vital statistics about Watts Bar Unit 2

Plant site

  • Location: Near Spring City in southeastern Tennessee
  • Acreage: 1,700-acre site on Chickamauga Reservoir

Cooling towers

  • Quantity: 2
  • Height: 506 feet
  • Diameter: 405 feet at ground level
  • Water flow: 410,000 gallons per minute

Switchyard

  • 500,000-volt transmission lines: 5
  • 161,000-volt transmission lines: 2

Plant design

  • Westinghouse pressurized water reactor that is expected to generate 1,150 megawatts (summer net capability)
  • Reactor core holds 193 fuel assemblies, each containing 264 fuel rods

Reactor vessel

  • Height: 43.8 feet
  • Weight: About 265 tons (empty)
  • Inside diameter: 14 feet
  • Steel thickness: About 9.4 inches
  • Operating temperature: About 586 degrees Fahrenheit
  • Operating pressure: About 2,235 pounds per square inch

Primary containment

  • Inside height: 197.3 feet
  • Inside diameter: 115 feet
  • Steel inner thickness: 1 inch
  • Design pressure: 15 pounds per square inch

Steam generators

  • Quantity: 4
  • Height: 67 feet 8 inches
  • Weight: About 380 tons
  • Operating temperature: About 600 degrees Fahrenheit
  • Operating pressure: 1,000 pounds per square inch

Main generator

  • Height: 16 feet
  • Length: 40 feet
  • Stator weight: About 1,000 tons
  • Rotor weight: About 200 tons
  • Ratings: 1,411 megawatts, 24,000 volts
  • Speed: 1,800 rotations per minute

Steam turbines

  • High pressure: A single eight-stage double-flow axial turbine
  • Low pressure: A series of three, eight-stage double-flow axial turbines
  • Maximum blade diameter: 16 feet
  • Rotor weight: About 177 tons

Main condenser

  • Tubes: About 27,410
  • Tube length: About 115 feet
  • Tube diameter: 1 inch

 

Content for id "future1" Goes Here
Content for id "future2" Goes Here
Content for id "future3" Goes Here