Sequoyah Nuclear Unit 2 Back Online Early And Under Budget

January 11, 2013

SODDY DAISY, Tenn. – Tennessee Valley Authority announced Friday the safe and successful completion of the Unit 2 refueling and maintenance outage at Sequoyah Nuclear Plant, finishing the work ahead of schedule and under budget.

The 83-day outage began on Oct. 15, 2012, and was completed on Jan. 6. The Sequoyah Unit 2 refueling and maintenance outage and steam generator replacement project was scheduled for 90 days and budgeted for $376 million. Actual costs for this outage will be finalized in the coming weeks but the plant’s leadership team is confident the final cost will be under budget.

“We are committed to the safe and efficient operation of TVA’s nuclear plants to ensure we provide reliable nuclear power to the people who live and work in the Valley,” Preston Swafford, TVA’s Chief Nuclear Officer, said. “The steam generator replacement project was a complex feat of design, engineering and skilled craftsmanship. I’m extremely proud of the nuclear professionals who worked tirelessly to manage this outage at Sequoyah Unit 2 safely, with careful attention to costs and schedule, all while continuing to operate Unit 1 at 100 percent power.”

The four steam generators that were replaced are massive heat exchangers that generate large volumes of steam to spin a turbine-generator to make electricity. TVA has also completed similar steam generator replacement projects at Sequoyah Unit 1 in 2003 and at Watts Bar Nuclear Plant’s Unit 1 in 2006.

Including Sequoyah plant personnel, contractors, craft, and other temporary workers there were nearly 3,000 people involved in this outage. Thirteen hundred temporary workers were involved in the safe replacement of the steam generators which required approximately one million work hours; all completed without a single lost-time incident.

Additionally, about 1,000 temporary workers supported the refueling and maintenance of Unit 2. Refueling and maintenance work cannot be done while Unit 2 is online so in addition to refueling Unit 2, every reasonable effort was made to complete additional major modifications to valves, pumps, electrical systems and the switchyard.  This work further ensures the efficient operation of the plant to reliably generate power at 100 percent until the next refueling outage.

Sequoyah Unit 2 is one of six nuclear power generating units operated by TVA at three facilities, supplying more than 30 percent of TVA’s electric generation capacity and helping to fulfill TVA’s vision of being a national leader in the production of clean, low-cost energy.

The Tennessee Valley Authority, a corporation owned by the U.S. government, provides electricity for business customers and distribution utilities that serve 9 million people in parts of seven southeastern states at prices below the national average. TVA, which receives no taxpayer money and makes no profits, also provides flood control, navigation and land management for the Tennessee River system and assists utilities and state and local governments with economic development.

Media Contact

Ray Golden, TVA Nuclear Communications, 423-751-8400
TVA Public Relations, Knoxville, (865) 632-6000
www.tva.com/news

image of swearing in

View high-res image

A 45-by-20-foot section of the Sequoyah Unit 2 reactor building, weighing 165 tons is lowered to the ground starting the process for steam generator replacement.

 

image of swearing in

View high-res image

Wrapped in a blue tarp, one of the four, 70-foot long, 345 ton original steam generators is removed from the Sequoyah Unit 2 reactor building.

 

image of swearing in

View high-res image

To ensure on-going safe and reliable plant operation, one of four new steam generators is being lifted and placed inside the reactor building. The now completed project should allow Sequoyah Unit 2 to operate for up to 30 additional years, providing clean, safe, and reliable power to 650,000 homes and businesses in the Tennessee Valley.

           